Cedar Creek Wind Farm
Grover, Colorado
• OH and UG collection system design
• Procure all materials for OH and UG collection system
• Pad mounts
• Trench and place 35kv cable
• 35kv splicing and cross-bonding
• HV & LV terminations
• WTG grounding and embedment
• Install and terminate junction boxes
• OH line construction
• Testing and commissioning